T3 Central Search Refurbishment

projectdescription

Complete refurbishment of the central Search Area in the extremely busy Terminal 3.

value

£16 million, in 2 phases over 20 months programme duration.

role

Client Project Manager.

commentary

Terminal 3 was an aging terminal, and the central Search refurbishment was part of a major programme to bring the terminal into the 21 century.

The terminal operates at full capacity during certain times of the year, so the passenger flow data had to be carefully considered to calculate how many security lanes could be removed from service at a time to allow the works to be carried out.

The works included new entrances to the CSA, integrated media sites, full refurbishment of walls , floors and ceilings, and all necessary IT modifications to CCTV and security lanes.

The works were completed ahead of programme.